Putting cows on the front page since 1885.

Work Complete On RS Water Tank

By RICK BOSTON

Staff Writer

Back in July, the Roaring Spring Municipal Authority began the process to paint and clean the borough's one-million gallon water tank by voting to advertise for bids.

The authority had sent a diver into the tank earlier in the spring to inspect the condition of the inside of the tank, and determined that both the outside and inside of the tank needed to be painted.

The authority then awarded the contract to L&T Painting of Michigan to sandblast, prime and paint the inside and outside of the tank, for $289,000.

Before work could begin the tank needed to be empty,...

 

Reader Comments(0)