Putting cows on the front page since 1885.

C-K Approves Order Changes, Votes to Seek Proposals for Athletic Project Work

At its Nov. 9 meeting, the Claysburg-Kimmel School Board approved some change orders that add an additional $53,843 to the cost of the district’s athletic project. L.S. Fiore, the project’s contractor, requested and received approval of $4,633.68 to remove a pavement low spot and adjust the grade for drainage; $40,496.68 to install 15-inch pipe from Athletic Drive to the Rain Garden; and $8,713.37 to remove unusable soil and install structural fill for the bleacher foundations. Board Vice President Craig Burket was the lone no vote.

The board also authorized the administration to seek...

 

Reader Comments(0)

 
 
Rendered 04/29/2024 11:05