Stiffler McGraw Engineer Jon Clabaugh talked about estimates following last month’s discussion of sewer replacement in Robeson Extension. Clabaugh said the cost estimates were “high” and that they included using a two-inch line. Estimates totaled $46,000-64,000, the higher total soliciting grinder pumps, too. For the extension to reach the remaining two residents on the same side as existing customers, the cost estimates were $85,000-$120,000. Daryl Cole made the motion to advertise for bids for the sewer line to Everhart property in the Extension with Chet Bingham seconding. The motion passed...